| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | ProductDashboard 1.0 | 106 days | Mon 3/17/03 | Mon 8/11/03 | | 100% |
| 2 | Research | 9 days | Mon 3/17/03 | Thu 3/27/03 | | 100% |
| 3 | Meeting - Gather Requirements | 1 day | Mon 3/17/03 | Mon 3/17/03 | Customer,Consultant | 100% |
| 4 | Write Requirements Report | 3 days | Tue 3/18/03 | Thu 3/20/03 | Consultant | 100% |
| 5 | Meeting - Review Requirements | 1 day | Fri 3/21/03 | Fri 3/21/03 | Customer,Consultant | 100% |
| 6 | Update Requirements Report | 2 days | Mon 3/24/03 | Tue 3/25/03 | Consultant | 100% |
| 7 | Meeting - Review Requirements | 1 day | Wed 3/26/03 | Wed 3/26/03 | Customer,Consultant | 100% |
| 8 | Update Requirements Report | 1 day | Thu 3/27/03 | Thu 3/27/03 | Consultant | 100% |
| 9 | Specification | 20 days | Fri 3/28/03 | Thu 4/24/03 | | 100% |
| 10 | Write Use Cases | 2 days | Fri 3/28/03 | Mon 3/31/03 | Consultant | 100% |
| 11 | Meeting - Review Use Cases | 1 day | Tue 4/1/03 | Tue 4/1/03 | Customer,Consultant | 100% |
| 12 | Update Use Cases | 1 day | Wed 4/2/03 | Wed 4/2/03 | Consultant | 100% |
| 13 | Meeting - Review Use Cases | 1 day | Thu 4/3/03 | Thu 4/3/03 | Customer,Consultant | 100% |
| 14 | Write Functional Specification | 5 days | Fri 4/4/03 | Thu 4/10/03 | Consultant | 100% |
| 15 | Meeting - Review Functional Specification | 1 day | Fri 4/11/03 | Fri 4/11/03 | Customer,Consultant | 100% |
| 16 | Update Functional Specification | 2 days | Mon 4/14/03 | Tue 4/15/03 | | 100% |
| 17 | Meeting - Review Functional Specification | 1 day | Wed 4/16/03 | Wed 4/16/03 | Customer,Consultant | 100% |
| 18 | Update Functional Specification | 1 day | Thu 4/17/03 | Thu 4/17/03 | Consultant | 100% |
| 19 | Write Design Specification | 3 days | Fri 4/18/03 | Tue 4/22/03 | Development | 100% |
| 20 | Meeting - Review Design Specification | 1 day | Wed 4/23/03 | Wed 4/23/03 | Consultant,Development | 100% |
| 21 | Update Design Specification | 1 day | Thu 4/24/03 | Thu 4/24/03 | Development | 100% |
| 22 | Submit Fixed Proposal | 0 days | Thu 4/24/03 | Thu 4/24/03 | Development | 100% |
| 23 | Implementation | 60 days | Fri 4/25/03 | Thu 7/17/03 | | 100% |
| 24 | Base Level 1 | 10 days | Fri 4/25/03 | Thu 5/8/03 | Development | 100% |
| 25 | Base Level 2 | 10 days | Fri 5/9/03 | Thu 5/22/03 | Development | 100% |
| 26 | Base Level 3 | 10 days | Fri 5/23/03 | Thu 6/5/03 | Development | 100% |
| 27 | Alpha Release | 10 days | Fri 6/6/03 | Thu 6/19/03 | Development | 100% |
| 28 | Beta Release 1 | 10 days | Fri 6/20/03 | Thu 7/3/03 | Development | 100% |
| 29 | Beta Release 2 | 10 days | Fri 7/4/03 | Thu 7/17/03 | Development | 100% |
| 30 | Quality Assurance | 30 days | Fri 6/20/03 | Thu 7/31/03 | | 100% |
| 31 | Alpha Release | 10 days | Fri 6/20/03 | Thu 7/3/03 | Consultant,Quality Assurance | 100% |
| 32 | Beta 1 Release | 10 days | Fri 7/4/03 | Thu 7/17/03 | Customer,Consultant,Quality Assurance | 100% |
| 33 | Beta 2 Release | 10 days | Fri 7/18/03 | Thu 7/31/03 | Customer,Consultant,Quality Assurance | 100% |
| 34 | Manufacturing | 7 days | Fri 8/1/03 | Mon 8/11/03 | | 100% |
| 35 | Master Release Kit | 3 days | Fri 8/1/03 | Tue 8/5/03 | Release Engineering | 100% |
| 36 | Write Release Notes | 2 days | Wed 8/6/03 | Thu 8/7/03 | Documentation,Release Engineering,Quality Assurance | 100% |
| 37 | Write Install Guide | 2 days | Fri 8/8/03 | Mon 8/11/03 | Documentation,Release Engineering | 100% |
| 38 | First Customer Ship | 0 days | Mon 8/11/03 | Mon 8/11/03 | Customer,Release Engineering | 100% |