ProductDashboard 1.0





Project Start:
Project Finish:
Mon 3/17/03
Mon 8/11/03


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
ProductDashboard 1.0
106 daysMon 3/17/03Mon 8/11/03 100%
2
Research
9 daysMon 3/17/03Thu 3/27/03 100%
3
Meeting - Gather Requirements
1 dayMon 3/17/03Mon 3/17/03Customer,Consultant100%
4
Write Requirements Report
3 daysTue 3/18/03Thu 3/20/03Consultant100%
5
Meeting - Review Requirements
1 dayFri 3/21/03Fri 3/21/03Customer,Consultant100%
6
Update Requirements Report
2 daysMon 3/24/03Tue 3/25/03Consultant100%
7
Meeting - Review Requirements
1 dayWed 3/26/03Wed 3/26/03Customer,Consultant100%
8
Update Requirements Report
1 dayThu 3/27/03Thu 3/27/03Consultant100%
9
Specification
20 daysFri 3/28/03Thu 4/24/03 100%
10
Write Use Cases
2 daysFri 3/28/03Mon 3/31/03Consultant100%
11
Meeting - Review Use Cases
1 dayTue 4/1/03Tue 4/1/03Customer,Consultant100%
12
Update Use Cases
1 dayWed 4/2/03Wed 4/2/03Consultant100%
13
Meeting - Review Use Cases
1 dayThu 4/3/03Thu 4/3/03Customer,Consultant100%
14
Write Functional Specification
5 daysFri 4/4/03Thu 4/10/03Consultant100%
15
Meeting - Review Functional Specification
1 dayFri 4/11/03Fri 4/11/03Customer,Consultant100%
16
Update Functional Specification
2 daysMon 4/14/03Tue 4/15/03 100%
17
Meeting - Review Functional Specification
1 dayWed 4/16/03Wed 4/16/03Customer,Consultant100%
18
Update Functional Specification
1 dayThu 4/17/03Thu 4/17/03Consultant100%
19
Write Design Specification
3 daysFri 4/18/03Tue 4/22/03Development100%
20
Meeting - Review Design Specification
1 dayWed 4/23/03Wed 4/23/03Consultant,Development100%
21
Update Design Specification
1 dayThu 4/24/03Thu 4/24/03Development100%
22
Submit Fixed Proposal
0 daysThu 4/24/03Thu 4/24/03Development100%
23
Implementation
60 daysFri 4/25/03Thu 7/17/03 100%
24
Base Level 1
10 daysFri 4/25/03Thu 5/8/03Development100%
25
Base Level 2
10 daysFri 5/9/03Thu 5/22/03Development100%
26
Base Level 3
10 daysFri 5/23/03Thu 6/5/03Development100%
27
Alpha Release
10 daysFri 6/6/03Thu 6/19/03Development100%
28
Beta Release 1
10 daysFri 6/20/03Thu 7/3/03Development100%
29
Beta Release 2
10 daysFri 7/4/03Thu 7/17/03Development100%
30
Quality Assurance
30 daysFri 6/20/03Thu 7/31/03 100%
31
Alpha Release
10 daysFri 6/20/03Thu 7/3/03Consultant,Quality Assurance100%
32
Beta 1 Release
10 daysFri 7/4/03Thu 7/17/03Customer,Consultant,Quality Assurance100%
33
Beta 2 Release
10 daysFri 7/18/03Thu 7/31/03Customer,Consultant,Quality Assurance100%
34
Manufacturing
7 daysFri 8/1/03Mon 8/11/03 100%
35
Master Release Kit
3 daysFri 8/1/03Tue 8/5/03Release Engineering100%
36
Write Release Notes
2 daysWed 8/6/03Thu 8/7/03Documentation,Release Engineering,Quality Assurance100%
37
Write Install Guide
2 daysFri 8/8/03Mon 8/11/03Documentation,Release Engineering100%
38
First Customer Ship
0 daysMon 8/11/03Mon 8/11/03Customer,Release Engineering100%

Resources


IDNameGroupMax UnitsPeak Units
1ConsultantConsulting100%0%
2CustomerCustomer100%0%
3DevelopmentDevelopment100%0%
4DocumentationDocumentation100%0%
5Quality AssuranceQA100%0%
6Release EngineeringRelease Engineering100%0%

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete
3Meeting - Gather RequirementsCustomer8 hrsMon 3/17/03Mon 3/17/03100%
3Meeting - Gather RequirementsConsultant8 hrsMon 3/17/03Mon 3/17/03100%
4Write Requirements ReportConsultant24 hrsTue 3/18/03Thu 3/20/03100%
5Meeting - Review RequirementsCustomer8 hrsFri 3/21/03Fri 3/21/03100%
5Meeting - Review RequirementsConsultant8 hrsFri 3/21/03Fri 3/21/03100%
6Update Requirements ReportConsultant16 hrsMon 3/24/03Tue 3/25/03100%
7Meeting - Review RequirementsCustomer8 hrsWed 3/26/03Wed 3/26/03100%
7Meeting - Review RequirementsConsultant8 hrsWed 3/26/03Wed 3/26/03100%
8Update Requirements ReportConsultant8 hrsThu 3/27/03Thu 3/27/03100%
10Write Use CasesConsultant16 hrsFri 3/28/03Mon 3/31/03100%
11Meeting - Review Use CasesCustomer8 hrsTue 4/1/03Tue 4/1/03100%
11Meeting - Review Use CasesConsultant8 hrsTue 4/1/03Tue 4/1/03100%
12Update Use CasesConsultant8 hrsWed 4/2/03Wed 4/2/03100%
13Meeting - Review Use CasesCustomer8 hrsThu 4/3/03Thu 4/3/03100%
13Meeting - Review Use CasesConsultant8 hrsThu 4/3/03Thu 4/3/03100%
14Write Functional SpecificationConsultant40 hrsFri 4/4/03Thu 4/10/03100%
15Meeting - Review Functional SpecificationCustomer8 hrsFri 4/11/03Fri 4/11/03100%
15Meeting - Review Functional SpecificationConsultant8 hrsFri 4/11/03Fri 4/11/03100%
17Meeting - Review Functional SpecificationCustomer8 hrsWed 4/16/03Wed 4/16/03100%
17Meeting - Review Functional SpecificationConsultant8 hrsWed 4/16/03Wed 4/16/03100%
18Update Functional SpecificationConsultant8 hrsThu 4/17/03Thu 4/17/03100%
19Write Design SpecificationDevelopment24 hrsFri 4/18/03Tue 4/22/03100%
20Meeting - Review Design SpecificationConsultant8 hrsWed 4/23/03Wed 4/23/03100%
20Meeting - Review Design SpecificationDevelopment8 hrsWed 4/23/03Wed 4/23/03100%
21Update Design SpecificationDevelopment8 hrsThu 4/24/03Thu 4/24/03100%
22Submit Fixed ProposalDevelopment0 hrsThu 4/24/03Thu 4/24/03100%
24Base Level 1Development80 hrsFri 4/25/03Thu 5/8/03100%
25Base Level 2Development80 hrsFri 5/9/03Thu 5/22/03100%
26Base Level 3Development80 hrsFri 5/23/03Thu 6/5/03100%
27Alpha ReleaseDevelopment80 hrsFri 6/6/03Thu 6/19/03100%
28Beta Release 1Development80 hrsFri 6/20/03Thu 7/3/03100%
29Beta Release 2Development80 hrsFri 7/4/03Thu 7/17/03100%
31Alpha ReleaseConsultant80 hrsFri 6/20/03Thu 7/3/03100%
31Alpha ReleaseQuality Assurance80 hrsFri 6/20/03Thu 7/3/03100%
32Beta 1 ReleaseCustomer80 hrsFri 7/4/03Thu 7/17/03100%
32Beta 1 ReleaseConsultant80 hrsFri 7/4/03Thu 7/17/03100%
32Beta 1 ReleaseQuality Assurance80 hrsFri 7/4/03Thu 7/17/03100%
33Beta 2 ReleaseCustomer80 hrsFri 7/18/03Thu 7/31/03100%
33Beta 2 ReleaseConsultant80 hrsFri 7/18/03Thu 7/31/03100%
33Beta 2 ReleaseQuality Assurance80 hrsFri 7/18/03Thu 7/31/03100%
35Master Release KitRelease Engineering24 hrsFri 8/1/03Tue 8/5/03100%
36Write Release NotesDocumentation16 hrsWed 8/6/03Thu 8/7/03100%
36Write Release NotesRelease Engineering16 hrsWed 8/6/03Thu 8/7/03100%
36Write Release NotesQuality Assurance16 hrsWed 8/6/03Thu 8/7/03100%
37Write Install GuideDocumentation16 hrsFri 8/8/03Mon 8/11/03100%
37Write Install GuideRelease Engineering16 hrsFri 8/8/03Mon 8/11/03100%
38First Customer ShipCustomer0 hrsMon 8/11/03Mon 8/11/03100%
38First Customer ShipRelease Engineering0 hrsMon 8/11/03Mon 8/11/03100%